US Builds a $43-Million Gas Station in Afghanistan and Nobody Seems to Know Why

The pumps at the CNG filling station constructed by TFBSO.  Photo credit:  SIGAR.MIL (PDF)

These are the facts. At some point, someone somewhere in the US government had an amazing idea: why not build a compressed natural gas (CNG) filling station in Afghanistan? Forty-three million taxpayer dollars later, the city of Sheberghan, in the far north of the country, got its gas station. But, according to the watchdog agency probing Afghanistan reconstruction spending, nobody seems to know — or wants to admit — who signed off on the project or how its costs spiraled so completely out of control.

The whole thing is so strange and wrongheaded that the crazily high price tag — more than 100 times what a similar facility would cost in neighboring Pakistan — is not even the worst thing the Special Inspector General for Afghanistan Reconstruction (SIGAR) found.

Natural Gas? For what Cars?

Even more troubling than the high price tag is that there was no point in building the gas station in the first place. While Afghanistan has vast natural gas reserves, it does not have a sufficient number of cars that run on natural gas, and converting a vehicle literally costs as much as the average Afghan earns in a year.

Had a feasibility study been conducted, somebody probably would have figured this out, but SIGAR found no evidence of such a precaution having been taken.

You might think the Department of Defense (DOD) would want to get to the bottom of this waste of money. After all, the project was part of the Task Force for Stability and Business Operations (TFBSO), which was created by the Deputy Secretary of Defense and reported directly to the Office of the Secretary.

Instead, DOD stonewalled.

“One of the most troubling aspects of this project is that the Department of Defense claims that it is unable to provide an explanation for the high cost of the project or to answer any other questions concerning its planning, implementation, or outcome,” SIGAR John Sopko wrote in a letter to Defense Secretary Ashton Carter.

Did the Dog Eat the Records?

DOD’s excuse for its lack of cooperation is that TFBSO, an $800 million program, was shut down in March of 2015 and now nobody is around to address SIGAR’s questions. That didn’t sit well with Sopko, who recently gave an exclusive interview to WhoWhatWhy in which he discussed the staggering amount of taxpayer funds wasted in Afghanistan.

“Frankly, I find it both shocking and incredible that DOD asserts that it no longer has any knowledge about TFBSO, an $800 million program that reported directly to the Office of the Secretary of Defense and only shut down a little over six months ago,” he wrote to Carter.

Sopko vowed to continue the investigation to determine “whether any conduct by TFBSO staff or contractors was criminal in nature” — as opposed to just crazily lucrative — for some well-connected insiders.


Related front page panorama photo credit: CNG Pump Nozzle (Andreas Geick / Wikimedia).

Where else do you see journalism of this quality and value?

Please help us do more. Make a tax-deductible contribution now.

Our Comment Policy

Keep it civilized, keep it relevant, keep it clear, keep it short. Please do not post links or promotional material. We reserve the right to edit and to delete comments where necessary.

print

8 responses to “US Builds a $43-Million Gas Station in Afghanistan and Nobody Seems to Know Why”

  1. VoxFox says:

    Corrupt countries behave like this.
    Can the USA save itself?

    • Jonn Mero says:

      Yeah, and when it comes to corruption, no country or institution beats the US DoD!

    • Wolfmates says:

      It is coming very close to the time where we will see if the USA can indeed save itself. More and more Americans are waking up and taking a stand. The question … is it in time? Stay tuned.

  2. Wolfmates says:

    Maybe it’s for all the gas-powered robotic camels the US is building for their partners in the region.

  3. (Comment by reader @GrainOfSands) So MIC contractors could profit. USA keeps war profitable on the backs & lives of Americans

  4. Jake Blake says:

    So was this used to funnel money into a black project, or a corrupt politicians pocket?

  5. From Our Facebook Page says:

    (Comment by reader Louis Foussard) Surprise, surprise.

    And it’s all the other things that we’ll probably never read about (the billions of dollars in cash bribes and/or the millions of dollars of missing/lost cash) that makes everything we do in the Middle East not surprising at all.

  6. From Our Facebook Page says:

    (Comment by reader Barry Price) Next we’ll be hearing that ISIS has a fleet of Toyota trucks that run on LNG…

  7. […] whose salaries are US-taxpayer funded but who seem not even to exist except on paper. Or thegas station that cost an absurd $43 million to build, but that nobody uses and about which the Pentagon now has […]